Methods for estimating projects
Author:
Fluent Commerce
Changed on:
6 Feb 2024
Overview
Every company has a unique approach to project estimation, so there is no one-size-fits-all solution. This article covers the typical approaches used to estimate projects.
Key points
- How to approach project estimation
Approaching Project Estimation
A possible approach to estimation post-discovery is shown in the example provided below. A similar approach can be taken as a good jumping-off point in identifying the solution types, estimating task sizes and prioritising sprints as the project progresses to development.
Solution Type
Depending on the scope of the project, you may define these Possible Values separately, but as a point of reference, the Base solution could be the out-of-the-box solution you get from Fluent Commerce.
Estimation
Estimation again there is the T-shirt size understanding whether it is base or should be minimal effort (0 to 1) days. Small simple configuration ranging from 1 to 2 days. Medium, Large, all the way up to X-Large where it’s a complex custom solution that's gonna need to be designed and can potentially be 20 to 40 days.
Priority
In addition to identifying the solution type, and T-shirt estimates against each requirement, it is also important to run through the priority.
The MUST, SHOULD, COULD and Won’t is a good place to start to be able to prioritise the sprints as we move to development.